Menu

Bingöl Kiğı Hydroelectric Power Plant Project

Completed Projects

Bingöl Kiğı Hydroelectric Power Plant Project

Information on the energy investment and technical scope of the hydroelectric power plant project located in Kiğı, Bingöl.

Contact Us

Hydroelectric Energy Project

Transforming the Peri River’s 218-metre hydraulic head into energy.

Kiğı Dam and Hydroelectric Power Plant is a comprehensive hydroelectric energy investment with a total installed capacity of 180 MW, developed to harness the energy potential of the Peri River in the mountainous terrain of Kiğı, Bingöl.

Comprising integrated engineering structures ranging from a clay-core rockfill dam and diversion and power tunnels to a vertical intake structure, surge shaft and pressure shaft, the facility generates electricity through three Francis turbine-generator units. Construction began in 2010, reservoir impoundment took place in 2015, and the facility was commissioned in 2017.

Technical Project Scope

An integrated system extending from the dam body to power generation

Kiğı Dam and Hydroelectric Power Plant brings together large-scale engineering structures developed to store and convey water under controlled conditions and convert a 218-metre hydraulic head into electricity.

Dam Body

The main structure was constructed as a clay-core rockfill dam with a height of 147 metres above the thalweg, a crest length of 585 metres and a body volume of 23,000,000 m³.

Reservoir and Spillway

The dam reservoir has a water storage capacity of 570 million m³. Located in an excavated section on the left bank, the radial-gated spillway provides the controlled discharge of floodwaters with a capacity of 4,500 m³/s.

Diversion Tunnels

Two diversion tunnels with an internal diameter of 5 metres and respective lengths of 1,278 metres and 1,385 metres were constructed to safely divert the Peri River during construction.

Water Intake and Conveyance System

Water is drawn through a 76-metre-high vertical intake structure with a rectangular cross-section of 11.40 × 9.5 metres and conveyed into an 8,135-metre-long, concrete-lined horizontal power tunnel with a diameter of 5.5 metres.

Surge Shaft and Pressure Shaft

Water from the conveyance tunnel is directed into a cylindrical surge shaft measuring 112 metres in height and 10 metres in internal diameter, before reaching the powerhouse through a 100-metre-high, concrete-lined vertical pressure shaft with an internal diameter of 5 metres.

Powerhouse and Generation Units

Three Francis turbine-generator units housed in the powerhouse harness the Peri River’s 218-metre hydraulic head to generate electricity with a total installed capacity of 180 MW.

180 MW total installed capacity of the power plant
147 m height of the dam body above the thalweg
570 million m³ water storage capacity of the dam reservoir
3 Units Francis turbine-generator system

Engineering Approach

Large-scale hydroelectric infrastructure in challenging terrain

Kiğı Dam and Hydroelectric Power Plant is a comprehensive engineering project that integrates water storage, conveyance and power generation systems within the mountainous terrain of Bingöl.

Comprising the dam body, spillway, diversion tunnels, water intake structure, long power tunnel, surge shaft, vertical pressure shaft and power generation units, the system enables the reliable and efficient utilisation of the Peri River’s hydraulic potential.

  • Harnessing a 218-metre hydraulic head for power generation
  • Construction of a 147-metre-high clay-core rockfill dam
  • A crest length of 585 metres and body volume of 23,000,000 m³
  • Creation of a reservoir with a water storage capacity of 570 million m³
  • A radial-gated spillway system with a capacity of 4,500 m³/s
  • Diverting the river flow through two separate diversion tunnels
  • An 8,135-metre-long concrete-lined power tunnel
  • Flow control through a surge shaft and vertical pressure shaft
  • Achieving an installed capacity of 180 MW with three Francis turbine-generator units
  • Completion of reservoir impoundment in 2015 and commissioning in 2017