Menu

Adana Pozantı Karakuz Dam and Hydroelectric Power Project

Completed Projects

Adana Pozantı Karakuz Dam and Hydroelectric Power Project

Information on the dam structures, hydropower investment and technical scope of the Karakuz Dam and Hydroelectric Power Project in Pozantı, Adana.

Contact Us

Hydroelectric Energy

Transforming the hydroelectric potential of the Körkün River into energy through comprehensive engineering structures.

Karakuz Dam and Hydroelectric Power Plant is a comprehensive energy investment with an installed capacity of 76 MW, developed on the Körkün River within the boundaries of the Pozantı and Karaisalı districts of Adana.

Designed to generate 276 GWh of energy annually, the project constitutes an integrated hydroelectric generation system comprising a concrete dam body, diversion and power tunnels, cofferdams, access roads, a surge shaft, penstock, powerhouse, switchyard and power transmission line.

Technical Project Scope

Integrated energy infrastructure extending from the dam to the national grid

For the Karakuz Dam and Hydroelectric Power Plant Project, all principal components of the hydroelectric facility were planned together to regulate the water, convey it to the power plant through an extensive transmission system and generate electricity using a high hydraulic head.

Dam Body and Reservoir

The concrete dam body, with a crest length of approximately 200 metres and a height of 45 metres from the foundation, regulates the Körkün River and creates the reservoir required for hydroelectric generation.

Diversion Structures

To safely divert the river flow during construction, inlet and outlet structures, cofferdams and a diversion tunnel measuring 6 metres in diameter and 321 metres in length were constructed.

Power Tunnel

Water stored in the reservoir is conveyed to the power plant system through an 11-kilometre-long power tunnel with an internal diameter of 3.1 metres, constructed using two tunnel boring machines.

Surge Shaft and Penstock

Located near the outlet of the power tunnel, the surge shaft—56 metres deep and 12 metres in internal diameter—regulates flow variations, while the water is conveyed to the power plant through a 1,580-metre-long penstock.

Powerhouse and Turbine Units

Two Pelton turbines in the powerhouse utilise an approximately 530-metre hydraulic head to convert the high-pressure energy of the water into electricity with a total installed capacity of 76 MW.

Switchyard and Power Transmission

Electricity generated at the power plant is transmitted to the national grid through a 154 kV switchyard and a 32-kilometre power transmission line.

76 MW total installed capacity of the hydroelectric power plant
276 GWh planned annual energy generation of the power plant
11 km power tunnel constructed using two tunnel boring machines
530 m approximate hydraulic head utilised by the Pelton turbines

Engineering Approach

A high-head hydroelectric generation system in challenging terrain

Karakuz Dam and Hydroelectric Power Plant is a large-scale hydroelectric engineering project that harnesses the water potential of the Körkün River through long tunnels, high-pressure conveyance structures and Pelton turbines.

All structures extending from the dam site to the powerhouse and the national electricity grid were designed through an integrated approach, taking into account the terrain’s topographical characteristics and the 530-metre hydraulic head. Approximately 2,000,000 m³ of earthworks and 160,000 m³ of concrete works were completed within the scope of the project.

  • Concrete dam body with a crest length of approximately 200 metres
  • Main dam structure measuring 45 metres from the foundation
  • Reservoir with a surface area of 29 hm² and a total volume of 5.112 hm³
  • A 6.2-kilometre access road around the reservoir
  • Diversion tunnel measuring 6 metres in diameter and 321 metres in length
  • An 11-kilometre power tunnel excavated using two TBMs
  • Surge shaft measuring 56 metres deep and 12 metres in internal diameter
  • Penstock measuring 2 metres in internal diameter and 1,580 metres in length
  • A total installed capacity of 76 MW provided by two Pelton turbines
  • A 154 kV switchyard and 32-kilometre power transmission line